HEAVY CIVIL $50 MILLION TO $100 MILLION
HEAVY CIVIL $50 MILLION TO $100 MILLION WINNER
Perimeter Pile Upgrade”
Shimmick Construction for “301 Mission
Te Millennium Tower Foundation Stabilization project represents one of the most technically complex and high-profile foundation interventions ever executed on a high-rise residential structure. Located in downtown San Francisco, the 645-foot-tall tower had become
a national headline due to its significant settlement and lean — including approximately 18 inches of vertical sinking and 24 inches of tilt. Tis high- stakes project sought to stabilize the building, halt further movement, and regain public confidence in one of the city’s most prominent skyscrapers. Shimmick Construction retrofitted the foundation by installing 18 deep
foundation piles drilled to bedrock – some 300 feet below grade. Te complex operation took place on a severely limited footprint surrounded by active traffic. Despite initial skepticism and significant public scrutiny, Shimmick successfully completed the project on schedule and within budget. Also selected as a finalist in this category were Myers-Shea JV for “Yreka Complete Streets Rehabilitation” and Teichert Construction for “State Route 99 Merced CRCP Rehabilitation.”
Shimmick Construction received a Constructor award for 301 Mission Perimeter Pile Upgrade.
CALIFORNIA CONSTRUCTOR MARCH/APRIL 2026
23
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40