CONSTRUCTOR AWARDS
gas main, relocation of the sanitary sewer main, widening of the creek, building new, taller levees and building a new pedestrian and bike bridge. Teichert completed the project
ahead of schedule – delivering a flood control system designed to protect the surrounding commu- nities for the next 100 years. Also selected as finalist in this
category were: Shimmick Construction Co., Inc. for “Fish Passage Facilities Within the Alameda Creek Watershed,” and Sully-Miller Contracting Company for “Albion Riverside Park Project.”
Heavy Civil Over $100 Million Winner: Kiewit Infrastruc- ture West Co. for “Spill- ways, Oroville Emergency Recovery”
Teichert Construction received a Constructor Award for the San Francisquito Creek project.
and Teichert Construction for “Turlock SR-99 Rehabilitation Project.”
Heavy Civil $20-$100 Million Winner: Teichert Construction for “San Francisquito Creek”
Te San Francisquito Creek
Flood Control project was needed to provide flood protection to the cities of Palo Alto and East Palo Alto. Teichert Construction partnered with an unprecedented 32 agencies and stakeholders, including more than 60 decision makers, to work through a multitude of issues on the extremely challenging job. Te project raised the height of the
levees and included installing flood walls to prevent future flooding in the area. Environmental regulations by various permitting agencies had a major impact on the project. Restrictions related to working
around protected birds, fish and mice created a critical six-week work window for a large portion of the job. Work in this area included new PG&E
www.AGC-CA.org Te Oroville Spillways
Emergency Recovery Project is a tale of two spillways with one unwav-
ering challenge – time. In less than 18 months, Kiewit Infra- structure West Co. completed an emergency repair and rebuild of two massive spillways for the California Department of Water Resources at the nation’s tallest dam.
Te project
was required after heavy rain and snowmelt compromised the main spillway and damaged the emergency spillway, leading to the evacuation of nearly 200,000 people. On the main
spillway, crews demolished most of the remaining existing concrete spillway, excavated soil and rock to reach a solid rock foundation and batched and placed more than 340,000 cubic yards of RCC to fill the excavation. Tey also batched and placed nearly 140,000 cubic yards of structural and leveling concrete to reconstruct the spillway structure. Primary work at the emergency
spillway included construction of a 700,000-cubic-yard RCC splashpad, totaling 1.2 million square feet. Tat is supported by a 1,450-foot-long underground secant pile wall, built into bedrock at depths of 35 to 65 feet. Kiewit and DWR disproved
the skeptics, finishing phase one on schedule and completing the second phase ahead of schedule. Also selected as finalist in this category
was Dragados USA Inc.-Flatiron West Inc.-Sukut Construction Inc., A Joint Venture for “Calaveras Dam Replacement Project,” Flatiron-Kiewit, A Joint Venture for “Presidio Parkway Phase 2,” and Skanska-Rados, A Joint Venture for “Exposition Light Rail Transit, Phase 2.”
Continued on page 18
Kiewit Infrastructure West Co. received its
first of two Constructor Awards for the
Spillways, Oroville
Emergency Recovery project.
Associated General Contractors of California 17
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24