CONSTRUCTOR AWARDS project. Te contract involved work around
live track, requiring extensive coordi- nation with Caltrain operations. All work within 15 feet of the track was subject to various restrictions and tight timelines. Te project team devised solutions
that saved money and allowed work to be performed within the tight timeline of a single full rail outage rather than two separate rail outages as originally envisioned. Tis saved both client and contractor resources and minimized impacts to the traveling public by eliminating an entire weekend from the project schedule. Also selected as finalist in this category
was: Monterey Mechanical Co. for “WETA North Bay Operations and Maintenance Facility” – Mare Island Naval Shipyard.
Meeting the Challenge of the Difficult Job – Specialty Contractor Over $10 Million Constructor Winner: Shimmick
Construction Company, Inc. for “MUNI Blue Light Emergency Phone Replacement” – San Francisco
Te MUNI Bluelight project
consisted of installing a new emergency telephone system within the MUNI stations from Embar- cadero to West Portal station and within the Metro and Sunset tunnel in San Francisco. Shimmick Construction Co.
overcame challenging work access restrictions, work area locations, and
MUNI Blue Light Emergency Phone Replacement
Accepting 2 Constructor awards for Shimmick Construction Company, Inc. are, left to right: Randy Shelden, Michael Storer, Matt Azzi, Spencer Mullaney, and Brian Dotterer.
www.AGC-CA.org
shift durations in order to install the new system in a manner that did not interfere with the existing emergency phone system. All contract work took place during night shifts in order to not impact MUNI patrons during rush hour. Work within the MUNI tunnel had to be done during non-revenue service hours or specific shutdown periods. Access was difficult, and work had
to be planned to keep the public safe while balancing construction produc- tivity. Te owner issued a change that combined two formerly separate shutdown windows into a continuous 150-day shutdown. Shimmick worked diligently to rotate and provide rest for field crews to mitigate worker fatigue so the project could be completed safely and efficiently without impacting MUNI’s services. Shimmick delivered several
innovative solutions to improve worker safety and efficiency. For example, they utilized a dual drill press machine that could drill two holes at once. By improving the ergonomics of the drilling action, the drill press machine prevented injuries, improved
Thank You Sponsors! AGC thanks the following
sponsors for the AGC 2017 Awards program:
Excel Bonds & Insurance Services
First Foundation Bank Trench Shoring CliftonLarsonAllen LLP Diepenbrock Elkin Gleason LLP Dodge Data & Analytics EPIC Insurance Brokers GLA Corp. HCSS Mission Critical, LLC Moss Adams PlanGrid Travelers CIFAC Gelman LLP Griffith Company Hilfiker Retaining Walls Marina Landscape Sully-Miller Contracting Corp B.T. Mancini Herzog Contracting Corp
production and eliminated any safety hazards encountered when drilling concrete anchors. Te contractor also devised a
system for installation of power and communication cables in the tunnel that enabled multiple cables to be installed simultaneously, minimizing the work days and increasing production. Also selected as finalist in this category
Associated General Contractors of California 15
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28