This book includes a plain text version that is designed for high accessibility. To use this version please follow this link.
AIR QUALITY While most states don’t issue


an official certificate stating that a rink is in compliance with air quality standards, it wouldn’t hurt an ice arena owner or operator to create a statement or poster outlining the steps it takes to monitor and measure the air quality in the facility.


ARID-Ice scores ™


with a fog, condensation, mold and drip free environment for over 400 NHL,Triple A, Double A, Collegiate, Recreational Ice Rinks and Curling Clubs Across North America.


These facilities benefit from ARID-Ice desiccant dehumidification for full capacity enhanced humidity control while maintaining automatic indoor air quality.


ARID-Ice by Controlled Dehumidification has provided humidity andindoor air quality control technology to the Pittsburgh Penguins, New Jersey Devils, Jacksonville Barracudas, Florida Panthers, Houston Aero’s, University of Notre Dame and Penn State University just to name a few.


Contact our application specialists to learn how your arena can benefit from ARID-Ice technology. Call 810-229-7900 today.


Controlled Dehumidification ctrdh.com


Te owner or operator must continue corrective action until measurements show not more than 20 ppm of carbon monoxide and not more than 0.3 ppm of nitrogen dioxide in all areas of the arena building open to the public.


Follow-up Testing


Te owner or operator must conduct and document the following air quality tests to confirm the effectiveness of the corrective action:


• At 20-minute intervals until measurements show not more than 20 ppm of carbon monoxide and not more than 0.3 ppm of nitrogen dioxide.


• Twenty minutes after the next five uses of ice maintenance equipment.


• At least once per day for the subsequent three days of arena use. Report


Whenever corrective action is required, the owner or operator must submit a report to the commissioner, within five business days, that includes:


• An explanation of why corrective action was necessary.


• A description of the immediate corrective actions that were taken.


• A record of all air quality tests required. • An action plan to prevent a reoccurrence.


Arena Evacuation


Te owner or operator must evacuate an area of the arena building whenever:


• CO exceeds 83 ppm or NO2 exceeds 2.0 ppm for more than five minutes.


• CO exceeds 40 ppm or NO2 exceeds 0.6 ppm for more than one hour.


• CO exceeds 20 ppm or NO2 exceeds 0.3 ppm for more than two hours.


When evacuation is necessary, the owner or operator must 28 ISI EDGE FALL 2016


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40