■ Coordinating with private property owners. Working with private property owners during temporary construction easements is a near term challenge the team is tackling through “robust advance notification and close coordi- nation” said Saad. Te I-405 Improvement Project
Photo courtesy Orange County Transportation Authority
■ Maintenance of traffic coordi- nation. Freeway closures are only permitted at night, and certain
the freeway on the sequencing of bridge construction to minimize disruptions to the surrounding communities as best as possible.”
team is committed to overcoming whatever challenges comes its way over the next four years to ultimately deliver the massive and critically needed infrastructure project for California’s traveling public. “Te project is unique in the heavy
highway industry in California for its size and scope,” Saad concluded. “It’s the largest freeway project in California and requires signif- icant coordination across multiple
PUBLIC AGENCY CONSTRUCTION COMPLIANCE
KwikCompli
1 2 3
Download the KwikCompli app
EASY AS 1-2-3!
Upload a Project Picture
In uncertain times...
Fill-in the Details & Submit
You Can Remain Anonymous
We Investigate California Public Agencies When They Self-Perform New Construction Projects That Should Be Advertised For Bid To Local Contractors
Visit
cifac.org details
www.AGC-CA.org Associated General Contractors of California 15 lie the greatest opportunities.
Wendel Rosen’s construction attorneys help bring clarity to the rapid changes–in technology, project delivery systems and risk management–that are shaping the industry. Today’s construction companies need an innovative legal team that can offer a clear vision. We bring things into focus.
See what we’re talking about, visit:
www.calconstructionlawblog.com
wendel.com
closure types cannot be done simultaneously. “On a 16-miles project alignment, this is a daily and nightly challenge,” Saad noted. “Te project’s maintenance of traffic group, including all parties involved on the project collaborate daily to achieve solutions.
I-405 Project Fast Facts
Design-Build Contractor: OC 405 Partners (JV of OHL and Astaldi)
Scope: 16 miles of freeway improved 18+ bridges replaced or widened
Total Project Cost: $1.9 billion
Some Major Material Quantities: ■ About 300,000 cubic yards of concrete paving
■ Approximately 150,000 linear ft. of draining pipe
■ 150,000 cu. yd. of structural concrete
■ Over 30 million pounds of rebar ■ 172 retaining and soundwalls
Construction Start: Spring 2018 Slated Completion: 2023
government agencies and local munici- palities. Te project has a world-class team that’s on track to deliver new infrastructure that will service Orange County for decades to come.”
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24