SPECIALTY $10 MILLION AND OVER
BrightView for “SoFi Sports Stadium and Entertainment Complex” More than five years of design and construction went into creating the 300- acre SoFi Sports Stadium and Entertainment Complex in Inglewood, home to the LA Rams and the LA Chargers. BrightView’s contract included installation of irrigation and drainage pipe,
WINNER
plant material, placement of decorative gravel, cobble and boulders and the creation of water features including a 5.5-acre lake, 13 pools, an 8-foot waterfall and programmable shooting fountain. Te contractor overcame numerous challenges, including starting the
project six months later than originally planned. Time constraints and delays demanded detailed logistics. At least 10 cranes were setting large overhead structure and roof panels each day, a critical consideration as BrightView executed more than 700 crane lifts to install and set rock, soil and trees at various locations. Trough detailed scheduling, tracking and continuous communication
with the client, BrightView delivered the project on time and under budget with no OSHA recordable incidents. Also selected as finalists in this category was Royal Electric for “Twelve Bridges High School Project.”
BrightView received a Constructor award for SoFi Sports Stadium and Entertainment Complex.
18
CALIFORNIA CONSTRUCTOR MARCH-APRIL 2022
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40