“creates a safety culture on the job where all the workers are really looking out for each other,” DeLong said.
Second Half Push to Completion
Construction of the Chase Center
project was approximately 60 percent complete as of this July. If it tracks anything like the Warriors’ third- quarter push in many of their games, the project is clearly headed for a strong finish. Steady progress is evident in
virtually every corner of the project site. A symphony of seven large cranes, including two crawler cranes and five tower cranes, are frequently in motion, overseen by a full time “crane boss” who coordinates their every move. A major focus of work this summer
was structural steel erection, including installing the long-span roof trusses. Te high roof membrane work began in mid-July, and the metal panel and glass curtainwall exterior is soon to be installed. Interior trade work was progressing from floor to floor at a rapid pace. Te entire team is focused on the
key project milestone of having the building “dried-in” by November 1, allowing finish work to proceed unabated for the remaining nine months of construction. Final certif- icate of occupancy is scheduled for August 1, 2019. Tat is a date that Mortenson | Clark has no intention of missing, say McLamb and DeLong. Both men plan to be on hand when the Warriors play their first game in the new arena next October. Te opportunity to see fans’
reaction is one of the biggest rewards of working on a sports and enter- tainment project like this, DeLong noted. “When you open an office tower
or a hospital, the opening event is basically handing over the keys to the owner,” he said. “In the sports world, the opening event is shared with 18,000 people enjoying the fruits of your labor. It is something to be there – a really great feeling. Tat’s part of the reason why I do what I do.”
www.AGC-CA.org
The Chase Center project is on track for an August 2019 completion.
NEED THIS? CALL US.
Trench Shoring Company was founded in 1973 on our commitment to provide the construction industry with the finest in shoring equipment, including Trench Tops™ (trench plates), Trench Shields™
, Hydraulic
Shoring, Slide Rail and additional under- ground equipment. We also offer same-day service from our ten locations.
Our dedication to safety and service are key to our growth and customer satisfac- tion. Trench Shoring Company will be there to service your most challenging job requirements.
10 Locations 800-423-4411
TrenchShoring.com
© 2018 Trench Shoring Company Associated General Contractors of California 15
For your toughest jobs you demand experienced professionals, backed by the largest inventory.
We deliver “THIS” and more!
Photo courtesy Mortenson | Clark, A Joint Venture
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28